Bringing two rooms together in Le Cannet: opening a stone load-bearing wall and enlarging an opening

Large living space in Le Cannet after opening the stone load-bearing wall, steel beams in place

OMPT GROUPE worked in Le Cannet, on the ground floor of a house, to bring two rooms together into one large living space. Between them stood a stone load-bearing wall, with an arched opening and a pier. On the next wall, an existing opening also had to be widened. Above, a reinforced concrete ring beam carries the upper floor: it had to stay in place during and after the works.

Our teams carried out the work according to the construction drawing from our engineering office OMPT STRUCTURE, which set the sections, the reinforcement and the order of each step.

Propping the floors and the roof structure

Before touching the stone, we propped the upper floor on both sides of the wall, with two rows of adjustable props and timber planks at the top and bottom to spread the loads. In the attic, a roof truss rested on this wall, so we placed an extra prop under its tie beam. The house was thus supported all the way, from the roof down to the ground.

Two reinforced concrete columns cast into the stone

A stone wall cannot carry a steel beam directly. We created two new supports: two 20 × 20 cm reinforced concrete columns, cast in pockets cut into the masonry and tied to the existing wall. The columns were built one after the other: work on the second only started once the concrete of the first had hardened, so the wall was never weakened in two places at the same time.

Installing the HEB 200 and HEB 180 beams

A chase was then cut under the reinforced concrete ring beam, and the HEB 200 steel beam was set on the two columns, then packed with wedges.

For the opening to be widened, we demolished the downstand under the ring beam, cast a reinforced concrete pad and installed a UPN 180 steel column, bedded in non-shrink mortar and anchored into the masonry. A second beam, an HEB 180, is joined to the first with two steel angles and six M16 bolts. The two beams form a corner that frames the new room.

Loading, demolition and removing the props

The wedges were driven in little by little so that the beams took up the weight of the floor, then the tops of the columns were packed with concrete. The pier and the wall between the columns could then be demolished. The props were removed step by step, checking that no cracks appeared and that the beams held well.

A large living space in Le Cannet

The ground floor is now a single open, bright space, under steel beams that carry the loads of the upper floor. The works were handed over without reservations on 19 November 2026.

OMPT GROUPE opens load-bearing walls in stone, concrete or blocks, installs steel beams (IPN, HEA, HEB, UPN) and creates floor openings in Le Cannet, Cannes, Mougins, Mandelieu-la-Napoule, Grasse and throughout the Alpes-Maritimes. Do you have a project? Request your quote.

Construction drawing of the opening in Le Cannet: HEB 180 beam joined to the HEB 200 beam, UPN 180 column and propping principle
Construction drawing produced by our engineering office OMPT STRUCTURE.