Structural reinforcement after demolition of load-bearing partitions in Cagnes-sur-Mer 06800

As part of an interior remodelling project for an apartment in Cagnes sur Mer, OMPT GROUPE stepped in to carry out a structural reinforcement solution following the demolition of several load-bearing partitions. The work was done following the method prescribed by the engineer.


Before any demolition, propping was set up beneath the partitions concerned to keep the structure safe during the works.


Pockets were cut into the load-bearing walls to receive the reinforced concrete bearings.
The steel sections were sealed onto the bearings with a shrinkage-compensated mortar, ensuring a reliable, lasting anchorage.


Steel shims were driven in between the underside of the floor and the sections to take up the structural load.


Once the structure was in place, the propping was removed, confirming the stability of the new assembly.
Do you have a remodelling project involving load-bearing partitions?


OMPT GROUPE, by your side to carry out your works with complete confidence.

Structural reinforcement after demolishing load-bearing partitions in Cagnes sur Mer 06800

06800 Cagnes-sur-Mer

Similar articles